| TIP: Click on subject to list as thread! | ANSI |
| echo: | |
|---|---|
| to: | |
| from: | |
| date: | |
| subject: | 2\21 TPS- Cosmos 1 Update - January 31 2003 |
This Echo is READ ONLY ! NO Un-Authorized Messages Please!
~~~~~~~~~~~~~~~~~~~~~~~~ ~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
delayed - This item just received at SpaceBase(tm)
The Cosmos 1 Update
January 31, 2003
Solar Sail Launch Awaits Clearing of Volna Rocket
by Project Director, Louis Friedman
The Planetary Society
The development of the Cosmos 1 solar sail spacecraft is going well
despite some delays with some of the spacecraft electronics. We are,
however, waiting for problems to be resolved with our launch vehicle,
the Volna. Until then, we are prisoners on Earth, trapped in our
planet's gravity well.
During the sub-orbital test launch in July 2001 the solar sails failed
to deploy because of problems during the test vehicle's separation
from the rocket. At the time we thought the vehicle failed to separate
from the launcher, but later events have cast doubt on that
assessment. In July 2002, a European payload failed to separate
properly from its Volna launcher during another sub-orbital flight.
Telemetry revealed that the problem was not a failure to separate, but
rather a premature separation of the payload while it was still inside
the second stage of the rocket.
An extensive failure commission set up by the Russian space agency
concluded that the cause of the 2001 and 2002 problems was most likely
the same. As a result they have grounded the Volna until changes to
the payload separation system can be implemented and thoroughly
tested.
It is strongly suspected that the payload separation problem was
caused by a malfunction of the second-third rocket stage separation.,
This is likely a result of a design change made when the Volna was
converted from an ICBM to a peaceful civil payload launcher. It seems
that the redesign of the joint between the second and third stages of
the rocket did not adequately account for the combination of forces
during launch
Correcting the problem is relatively simple, but the test program to
verify that it is correct is not. The Russian space agency is
demanding an extensive series of ground tests. These would involve,
among other things, a drop tower vacuum chamber in which the second
and third stage separation can be tested simulated free flight in
space. This test program will be conducted at the Makeev Rocket Design
Bureau in Miass, Russia. They are responsible for the Volna launch
vehicle.
Although regrettable, this is hardly a unique situation in the space
business. The recent failures of the Proton and Ariane 5 and other
examples show that payloads often have to wait for launch vehicles.
The Makeev test is currently scheduled for April, but it cannot begin
until they receive engineering hardware from our project at the
Babakin Center. That engineering model hardware is being used right
now in thermal-vacuum tests on the spacecraft. Once these tests are
completed, the model will be shipped to Makeev.
All components for the spacecraft, save one radio system, have now
been delivered and system tests are underway. The development of the
new S-band radio by our Russian and Ukrainian contractors has proved
more difficult than expected. Nevertheless, its completion should not
delay the spacecraft's assembly. The final assembly will probably be
done in late May or early June, after all ground tests on the
engineering model and electronics are complete.
The ground tests on the Volna will help determine whether another
sub-orbital test flight will be required. If it has to be done,
further delays are to be expected. Our hope is that the ground tests
will prove satisfactory, so that no sub-orbital flight will be
necessary. We, like our colleagues at Babakin and at Makeev have to
weigh the additional value of another flight test against the
diversion and delay it can cause. This is especially true as the
requirements for a sub-orbital flight are very different from orbital
flight requirements.
If the ground tests and verification of payload separation go well at
Makeev, and all spacecraft tests go well, we will launch about two
months after the final assembly. This means July at the earliest, but
possibly not until September.
Delays are disappointing and they cost us extra money. The failures
connected with the launch have also made us more sensitive to other
possible failures in getting the spacecraft into orbit and operating
successfully. We are making some additions to our flight plan to
increase reliability, and these too cost us money. This is typical in
aerospace work, but it is hard on a space-interest group working with
private funds.
Amid the trees, we must not lose sight of the forest. The launch
vehicle problem is completely unrelated to our solar sail spacecraft.
Solar sailing has not advanced since the mid 1970s because no one has
been able to procure an affordable launch vehicle and build a working
spacecraft. We still have the best hope of ANYONE to fly the first
solar sail mission.
- End of File -
================
---
* Origin: SpaceBase[tm] Vancouver Canada [3 Lines] 604-473-9357 (1:153/719)SEEN-BY: 633/267 270 @PATH: 153/719 715 7715 140/1 106/2000 633/267 |
|
| SOURCE: echomail via fidonet.ozzmosis.com | |
Email questions or comments to sysop@ipingthereforeiam.com
All parts of this website painstakingly hand-crafted in the U.S.A.!
IPTIA BBS/MUD/Terminal/Game Server List, © 2025 IPTIA Consulting™.