NASDA, Japan
2002/12/12
Y-1 (L-1) Operations Progressing Smoothly
-- 2 days before a launch --
=========================================
Launch preparation for the Advanced Earth Observing Satellite-II
(ADEOS-II)/H-IIA Launch Vehicle No.4 (H-IIA F4) now moved onto the Y-1
(L-1, or one day prior to the launch day) operations. Today's Y-1
(L-1) countdown operations started at 6:00 a.m.
Reception of radio frequencies (telemetry and data through radars)
transmitted from the launch vehicle to ground facilities was verified,
and propulsion systems such as engines were functionally confirmed.
The doors through which operators make access to the launch vehicle
were closed to complete all work which required to directly contact to
the vehicle.
ADEOS-II was powered up to verify its equipment functions. The total
number of Y-1 countdown operators reached 617.
- End of File -
================
---
* Origin: SpaceBase[tm] Vancouver Canada [3 Lines] 604-473-9357 (1:153/719)SEEN-BY: 633/267 270 @PATH: 153/719 715 7715 140/1 106/2000 1 379/1 633/267 |
|
| SOURCE: echomail via fidonet.ozzmosis.com | |
Email questions or comments to sysop@ipingthereforeiam.com
All parts of this website painstakingly hand-crafted in the U.S.A.!
IPTIA BBS/MUD/Terminal/Game Server List, © 2025 IPTIA Consulting™.