Jim,
I talked to Paul last night (he's been having to work double shifts at his
regular job).
The I/O boards should be delivered before Christmas... about a dozen a week
have been going out.
The paddle board parts are in their hands now; they got delayed twice. First,
from a company which turned out not to be able to deliver the order; then from
another company which raised prices on their parts unexpectedly.
One other "gotcha" they had... as we all know, the casemaker changed styles on
them a few months back. They added a PC backplate which had to first be
*removed*. Get this: at a cost of $40 per case! Personally, I would've just
told everyone to get their own case instead of eating the cost as he did.
Latest drivers/etc will be going out as a Christmas present, btw.